Project
Acute hospital — JCI survey readiness
PM Casey Sample (Demo Quality Lead)
Why delayed Close medication storage CAPA evidence +14d·Ask Demo decision: assign a CAPA owner and approve the mock survey evidence review.·Top risk Medication storage finding lacks verified corrective action evidence ahead of the mock survey. (16)·C-suite Medication storage finding lacks verified corrective action evidence ahead of the mock survey.
Auto-computed from critical-severity risks and blocked/overdue tasks — not manually edited.
Task grid
| Task | Phase | Flags | Planned | Current | Status | Progress | Owner | Files | Open |
|---|---|---|---|---|---|---|---|---|---|
CAPA60% avgJan 12, 2026 to Apr 10, 2026 | |||||||||
| Close medication storage CAPA evidence | CAPA | ! | Jan 12, 2026 to Mar 27, 2026 | Jan 12, 2026 to Apr 10, 2026 | in progress | 60% | Riley Example (Demo Owner) | 0 | |
Expand rowVariance +14d Last update 6/15/2026 Notes The ward finding needs a documented corrective action and verifier sign-off. Phase CAPA Task fields are read-only for your role. Dates move through request and approval only. AttachmentsNo attachments. Update history (1)
| |||||||||
Audit100% avgFeb 02, 2026 to Mar 06, 2026 | |||||||||
| Verify ward audit checklist | Audit | ! | Feb 02, 2026 to Mar 06, 2026 | Feb 02, 2026 to Mar 06, 2026 | done | 100% | Riley Example (Demo Owner) | 0 | |
Expand rowVariance 0d Last update 6/15/2026 Notes The ward round checklist and sample evidence are complete. Phase Audit Task fields are read-only for your role. Dates move through request and approval only. AttachmentsNo attachments. Update history (1)
| |||||||||
CAPA
Close medication storage CAPA evidence
Riley Example (Demo Owner)
in progressPlanned
Jan 12, 2026 to Mar 27, 2026
Current
Jan 12, 2026 to Apr 10, 2026
Progress
60%
Files
0
Close medication storage CAPA evidence
Riley Example (Demo Owner)
Planned
Jan 12, 2026 to Mar 27, 2026
Current
Jan 12, 2026 to Apr 10, 2026
Progress
60%
Files
0
Variance
+14d
Last update
6/15/2026
Notes
The ward finding needs a documented corrective action and verifier sign-off.
Phase
CAPA
Task fields are read-only for your role.
Dates move through request and approval only.
Attachments
No attachments.
Update history (1)
6/15/2026, 9:00:00 AM · Riley Example (Demo Owner) · Check in logged
Progress: empty to 60Status notes: empty to The ward finding needs a documented corrective action and verifier sign-off.Source: empty to demo
Audit
Verify ward audit checklist
Riley Example (Demo Owner)
donePlanned
Feb 02, 2026 to Mar 06, 2026
Current
Feb 02, 2026 to Mar 06, 2026
Progress
100%
Files
0
Verify ward audit checklist
Riley Example (Demo Owner)
Planned
Feb 02, 2026 to Mar 06, 2026
Current
Feb 02, 2026 to Mar 06, 2026
Progress
100%
Files
0
Variance
0d
Last update
6/15/2026
Notes
The ward round checklist and sample evidence are complete.
Phase
Audit
Task fields are read-only for your role.
Dates move through request and approval only.
Attachments
No attachments.
Update history (1)
6/15/2026, 9:00:00 AM · Riley Example (Demo Owner) · Check in logged
Progress: empty to 100Status notes: empty to The ward round checklist and sample evidence are complete.Source: empty to demo