Cognitive Wellness — Longevity clinic pilot

PM Assel Wanigasekara

Off track+46d
Why delayed Pura Longevity paid pilot signed +46d·Ask Approve pilot pricing for Pura Longevity so Dr. Rahat can sign this quarter.·Top risk Longevity clinic procurement stalls without a fixed price. (16)·C-suite Longevity clinic procurement stalls without a fixed price.

Auto-computed from critical-severity risks and blocked/overdue tasks — not manually edited.

Task grid

Unphased

50% avgMar 01, 2026 to Aug 15, 2026

CNS Vital Signs adapter live

Assel Wanigasekara

done

Planned

Mar 01, 2026 to May 15, 2026

Current

Mar 01, 2026 to May 15, 2026

Progress

100%

Files

0

Variance

0d

Last update

No update

Notes

No notes

Phase

Unphased

Task fields are read-only for your role.

Dates move through request and approval only.

Attachments

No attachments.

Update history (0)

No updates logged yet.

Pura Longevity paid pilot signed

Assel Wanigasekara

done

Planned

Mar 01, 2026 to Jun 30, 2026

Current

Mar 01, 2026 to Aug 15, 2026

Progress

0%

Files

0

Variance

+46d

Last update

8/4/2026

Notes

[2026-07-31 via email] Work is currently stalled due to a lack of feedback from the client. [KILLED 2026-08-04 per founder: warm/internal-longevity unconvertible — pilot was NOT signed; status=done used only to stop check-in nags (no cancelled state exists). Never cite as a win.]

Phase

Unphased

Task fields are read-only for your role.

Dates move through request and approval only.

Attachments

No attachments.

Update history (1)
  • 7/31/2026, 5:23:25 AM · Assel Wanigasekara · Check in logged

    Source: empty to emailProgress: empty to emptyStatus notes: empty to Work is currently stalled due to a lack of feedback from the client.